Site Power Infrastructure & Genset upgrade works

Date: 12/09/17

Customer: QIAGEN

Client: QIAGEN

Scheme of Works: Site Power Infrastructure & Genset upgrade works

The Brief:

When the Stockport & Manchester based Consultancy firm ECS Ltd were tasked to Design and Project Manage the Electrical Infrastructure Upgrade Works for Qiagen at Manchester Science Park, they chose CPS Ltd as the preferred supplier of the replacement Genset.  

The scheme of works included for de-commission and removal from site of the existing 400KVA Packaged Genset, as well as for the supply of a 200KVA Rental Genset to cover essential loads until the new 800KVA Packaged Genset had been fully commissioned and handed over.

The Conclusion

CPS Ltd co-ordinated works in-line with other contractors, ensuring an enhanced delivery of the project, thus allowing infrastructure upgrades to be fully operational to the Project Milestones.    

View all CPS Case Studies

CPS Backs Local Football Team

CPS Backs Local Football Team

25th October 2023

CPS sponsor Cockerham under 10's football Club

Read More

CPS BLOG

CPS Win Health & Safety Award!

CPS Win Health & Safety Award!

21st February 2022

CPS has been honoured with a prestigious award for Health and Safety Transformation at the British...

Read More

CPS BLOG

Head Office

Call 0845 437 9750

Email sales@central-power.co.uk

Parts Hotline

Call 0845 437 9750

Email parts@central-power.co.uk

Sales Enquiries

Call 01995 642 600

Contact enquiry form